City begins rehabilitation of Schuylkill Expressway/I-76 viaducts

April 5, 2019

The City has begun rehabilitation of two I-76 (Schuylkill Expressway) viaducts – in Center City and West Conshohocken. The project in Center City will include repairs or replacement of the concrete joints and deteriorated sections of the concrete deck, rehabilitating piers and columns, and repairing the viaduct’s drainage system.

Due to the project, overnight and weekend closures will take place intermittently from April to July at the following locations:

• University Avenue Exit 346B
• South Street On-Ramp
• South Street Exit 346A
• Walnut Street On-Ramp

The nearly $40 million project is expected to be completed in Fall 2020. More information is available at: https://i76viaduct.com/. For construction schedule, go here.