Google+

No trolley service to/from Center City July 31 – Aug. 17 (updated)

July 30, 2015

The annual Center City Trolley Tunnel maintenance and construction project (SEPTA Trolley Tunnel Blitz) is scheduled for July 31 – Aug. 17, 2015, which means there will be no trolley service in the tunnel during this period. Trolley Routes 10, 11, 13, 34 and 36 will not operate in the tunnel from 10 p.m. on Friday, July 31 through 4 a.m. on Monday, Aug. 17 while SEPTA crews complete a variety of power, track and station improvement projects.

During the 16-day tunnel closure, passengers can use the Market-Frankford Line from 40th Street station to travel to and from Center City. All trolleys will be diverted to 40th and Market Streets where passengers can switch to subway service at no additional cost.

During the Blitz, SEPTA crews will replace almost 7,500 feet (more than one mile) of track on the westbound side of the tunnel between 22nd Street Station and the 40th Street Portal.

1 Comments For This Post

  1. Strongforu Says:

    I know that the repairs are necessary and I’m glad they’re being done. However, why do they have to do this in the hottest frickin’ month of the year?!? Even though school-children and university students are off, the rest of us still have to trudge our way to center city for our desk jobs and now we have to use multiple modes of transportation to do it!

Leave a Reply

  +  45  =  46