septaroute36SEPTA is conducting trolley track work this summer on the Routes 10, 11, and 36 and residents should expect shuttle buses on these lines and limited traffic on the affected blocks.

A switch and track crossing renewal project for the intersection of 49th Street and Woodland Avenue will take place June 9-22 and service on SEPTA’s Route 11 and 36 trolleys will be affected during this two-week period. Normal construction hours will be Monday-Friday, 7 a.m.-8 p.m. and possibly on weekends if it is necessary for maintaining the project schedule. During the project, 49th Street and Woodland Avenue will be closed to traffic in all directions for a full block from the worksite. Here are more details on the changes in the operation of the 36 and 11 trolleys for the duration of the project (source: septa.org).

Route 36 Service:
• Buses will replace all trolleys from the Eastwick Loop to the 40th Street Portal.
Passengers traveling to Center City can board any trolley at the Portal for service to 13th
Street.

Route 11 Service:
• Eastbound, Route 11 trolleys will operate from the Darby Loop to 50th Street and
Woodland Avenue, then travel over 49th Street to Chester Avenue and on to the 40th
Street Portal for Center City destinations. Passengers needing to make stops on
Woodland between 50th Street and the 40th Street Portal can transfer to shuttle buses at
50th and Woodland.
• Westbound, trolleys will operate from 13th to 40th Streets via the Center City tunnel, then
travel on Woodland Avenue to Chester Avenue to 58th Street and back to Woodland for
service to the Darby Loop. Shuttle buses will be available at the 40th Street Portal for
customers that need to make stops on Woodland between the Portal and 57th Street.

SEPTA is also conducting a track renewal project on a portion of the Route 10 trolley line. During this project, which is expected to be completed by Aug. 31, 2013, tracks will be replaced on Lancaster Avenue from 40th to 44th Streets, the intersection at 48th Street and on 41st Street between Wallace Street and Lancaster Avenue.

The project will be completed in three phases. Shuttle bus service for the Route 10 trolley will be in effect between 63rd Street and Malvern Avenue to 33rd and Market Streets for the project’s second and third phases, June 23-August 31, 2013. Buses will also substitute trolley service on the Route 15 from August 18-24. For more information, visit SEPTA’s website or call SEPTA Customer Service at 215-580-7800.